 |
| Since the early 1900's, Folly Island has become
the most erosional
and highly developed island in S.C. Over the past 150 years, the shoreline
of Folly has retreated at rates of up to 10 feet per year (Lennon,
2000)! To combat this erosion, engineers have implemented the following
strategies to stabilize the sand: |
|
Jetties
Jetties are long man-made structures extending
perpendicular
from the shoreline into the ocean. These structures are used to
stabilize the sand and migration of inlets, and slow longshore
drift processes. They collect sand on the updrift side and
erode on the downstream side of the jetty. The cost of building
jetties can exceed $50,00 per linear foot.
|
|
|
The Charleston Harbor Jetties were completed
in 1898 to prevent sand from collecting in the entrance of the
harbor that kept ships from entering (Neal, et al, 1984). Each
of the two walls that make up the jetties, one extending from
Sullivans Island and the other from Morris Island, extends for
2.5 to 3 miles in length. These were constructed to keep sand
from accumulating and interfering with the ships' mobility in
and out of the harbor.
|
For 25 - 30 years after construction,
these structures did not cause erosion to Folly and Morris Islands.
In fact, Folly's shoreline grew seaward more than 2000 feet (Lennon,
2000) as remnant sand bars moved onshore by wave action. Within
30 years of the jetties construction, the growth of Morris and Folly
Islands worked to the demise of Charleston's ebb
tidal delta (Lennon, 2000). This delta served as the primary
location of sediment for Morris and Folly Islands. Sand from northern
islands is delivered to this area by longshore
currents and the Cooper and Ashley Rivers. By the 1930's, the
islands' sediment supply from the delta was depleted, resulting
in the return of the erosional state of both islands (Lennon, 2000).
Since then, the shorelines retreat at approximately four to six
feet per year.
|
|
Groins
Similar to jetties, yet smaller
in size, groins are hard structures constructed perpendicular
to the beach. They also cause erosion on the downdrift side of
the structure. The cost of building groins is roughly $2,000 per
linear foot. But construction of groins has been outlawed in most
states. The first series of groin construction on Folly Island
began in the 1940's. These were spaced 1000 feet apart and by
the 1950's, a second series of groins was added between the original
groins, resulting in a groin every 500 feet (Lennon, 2000). These
remained in tack or partially functional until Hurricane Hugo
struck the S.C. coast in 1989.
|
Photo provided by http://pbisotopes.ess.sunysb.edu/geo101_f00/
notes/11-1-00.htm
|
|
Folly Beach, SC
|
Picture courtesy of
L.R. Sautter.
|
|
|
|
Both of these structures, if working
properly, are successful in trapping sand. However, neighboring
islands on the downdrift side are depleted of sediment accumulation.
The construction of the Charleston Harbor Jetties
and groins has
modified the flow of sand along Morris and Folly Islands. Simply
stated, if jetties or groins are useful in trapping sand on one
island, they must be causing erosion on another!!!
|
For more information on the effects
of groins on South Carolina's beaches, click
here.
|
Seawalls
Like groins, these structures are
made of wood, steel, rock, or concrete. Seawalls are constructed
in front of buildings and parallel
to the beach. They are designed to receive the full brunt of an
incoming tide and
halt the retreat of a shoreline. This is a useful tool in securing
the property directly behind the seawall, however it is not without
negative environmental impacts. One of the most serious is the partial
reflection of the incoming wave energy. The sediment in front of
the wall is scoured and removed, thus facilitating erosion. Larger
and more costly seawalls must replace the former ones to combate
the loss of beach in front of it.
|

|
Folly Beach provides a perfect
example of the use of seawalls and their consequent destruction.
The Holiday Inn (now called Charleston by the Sea) is the most dominant
structure on the island and is built in a perilous location. The
recreational beach would not exist, even at low tide, in front of
this structure if it were not frequently renourished
(see next section). Ironically, the seawall returns the sediment
(brought from the inlet to renourish the beachfront) to its original
location
|
Seawall located in front
of the Holiday Inn (Folly Beach, SC). Photo provided by
Elizabeth Rogers
|
|
Beach Renourishment
The building of dunes and construction
of the upper beach by depositing transported sand is commonly referred
to as beach renourishment. This is the most nonevasive approach
to beach reparation. Often, the sand is dredged
from the back side of the island or from the continental
shelf (Neal et al., 1984). The latter location is preferred,
however it is the most costly. Often, the sand from the backside
of the island tends to be too fine, thus facilitating erosion. If
the sand is too coarse, the recreational quality of the beach is
compromised.
|
Does it work? Yes, but on the short
term. Renourshment is a costly process and must be continually implemented
for optimal results. For example, in 1993 the Army Corps of Engineers
completed the first stage of a fifty year project. This project
was planned with the intention of renourishing every eight years.
In the first stage in 1993, fifteen to eighteen million dollars
was spent on Folly Island's renourishment. Approximately 2.5 million
cubic yards of sand was pumped from the backside of the island and
deposited over a length of 5.34 miles, from the south tip to the
middle part of the shoreline (Lennon, 2000).
|
By 1995, approximately two thirds
of the added sand had eroded. The Charleston County Park at the
southern end of the island, in particular, suffered a significant
loss of sand. The severe erosion at the park was linked to the Army
Corps of Engineer’s 1993 renourishment project as the source of
sand for the renourishment was the Stono Inlet in the Folly River.
Removal of sand behind the island (in the river) upset the natural
balance and sand from the park began to fill in the vacancies left
by the dredging (Lennon, 2000).
|
An emergency renourishment was
implemented in April 1998 at the southern end of Folly Island due
to the advanced erosional state of the county park (coastalhazards.wcu.edu,
2001). The federal government deposited 90,000 cubic yards of sand.
It was determined that the Army Corps of Engineer's 1993 renourishment
project facilitated the erosion of the county park's beach. Therefore,
the federal government was required to spend nearly $315,000 in
retribution (Vettese, 2000).
|
Less than one year later, additional
renourishment was required due to sand from the 1998 renourishment
was gone and the park was continuing to erode. Only 130 of the original
400 parking spaces are left (as of December, 2001). To remedy the
situation, 49,000 cubic yards of sand was recently dredged from
the Folly River - enough for a 150 foot wide beach 1000ft long.
The $228,000 project was again paid for by the Army Corps of Engineers
(Vettese, 2000).
|
It is important to realize that
this is a financially intensive effort to save our beaches. Therefore,
it is common for only a part of a beach to be renourished at one
time.
|
Even though this method of beach
stabilization is preferred over jetty
and groin construction,
it is not without negative impacts. It can give uneducated investors,
developers, and homeowners the impression that Folly Island has
a healthy and stable beachfront, as well as a false sense of security.
This can lead to the development on land that is highly unstable.
It is important to remember erosion is a natural process of barrier
islands. With the increase in population
density on barrier islands, we must try to maintain the island's
fragile equilbrium. If we attempt to abate erosion on one island,
an adjacent island often will suffer.
|
To view images of Folly's beach renourishment
history, click here.
|
Download the following activity:
Creating Your Very Own Sand
Dunes, courtesy of http//:askeric.com
|
|
This
document is written in PDF format and requires Adobe
Acrobat Reader.
To download this free software, click on the Adobe button. |
 |
NOTE:
Each activity is correlated to the S.C. Science Curriculum
Standards
|
|
|

|
|